Reference Documents

Wednesday, December 04, 2013

Bankruptcy Here and There

Need I repeat the sad tale of the LOCSD's bankruptcy again? Well, I won't. But the bankruptcy lives on, perhaps to FINALLY end with the conclusion of these two meetings…one can hope anyway…too optimistic maybe…

Goodbye solid waste franchise, it's been nice knowing you.


Los Osos CSD meeting
Thursday, December 5, 2013
6:00 PM

2. CLOSED SESSION

A. PENDING LITIGATION (Government Code §54956.9(a).)
Conference with Legal Counsel Regarding Existing Litigation (Formally initiated:
-In re Los Osos Community Services District (ND-06-10548) United States Bankruptcy Court,
Central District of California, Northern Division


••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••

Board of Supervisors meeting
Tuesday, December 10, 2013
9:00 AM

Consent Agenda - Public Works Items:

9. Submittal of a resolution authorizing and directing the actions necessary to satisfy the conditions to effectiveness of the amended bankruptcy in In re the Los Osos Community Services District. District 2

Tuesday, November 26, 2013

Dig's Thanksgiving Post

The new post from Michelle this evening - the holiday schedule and a thank you!

Read it at this link:
http://www.diglososos.com/2013/11/25/holiday-work-thanksgiving/

Do NOT miss the photos at the bottom - really cute!

Thursday, November 21, 2013

Starting December for Dig Los Osos....

......new office hours:

Off the Dig site:

Effective 12/1/13 office hours will be held only on Thursdays from 9 am to 11 am, or by appointment.

http://www.diglososos.com/contact/

Wednesday, November 20, 2013

LOCSD Special Meeting Today Cancelled!

I wonder what that means?

Sewer Geeks! Important Water Board Update!

Friday, December 6, 2013, 8:30 a.m.
Save the date, don't miss this meeting!

Central Coast Water Board
895 Aerovista Place, Suite 101, San Luis Obispo

See the agenda and related documents off this link.

World Toilet Day!

Darn, we missed it, it was yesterday! Well, check out the link here to see what it was about. Be sure to click through all the pictures as they are rather fun! You can go out apparently to celebrate, or you can celebrate at home!


However, it is very sobering to see what the lack of sanitation can cause. An excellent book on the topic is The Big Necessity The Unmentionable World of Human Waste And Why It Matters by Rose George. A fascinating read.

Los Osos is having its own daily toilet celebration I guess, seeing that the aim of the World Toilet Day was SANITATION! Our sewer project is moving along swiftly in the attempt to clean up the disgusting fact of, dare I say it? (sure, why not, it's my blog), peeing and pooping right on top of our water supply! Ugh. UGH. UGH!

A major side note to the cleaning up of things beyond water in Los Osos will occur Wednesday afternoon, November 20, 4:00 p.m. at the District Office on 9th Street. The BANKRUPTCY. This meeting is for the directors to vote on transferring the solid waste franchise to the County for $2.8 million. Read all about the meeting here.

This quote out of the staff report outlines a brief history:
As a result of the District's termination of the wastewater project being constructed under contract to the District, the creditors filed a series of claims and initiated legal action against the District.  As a result of those actions, the District declared Bankruptcy in August of 2006. The total amount of the creditor's claims at that time exceeded $46,500,000.
The bankruptcy was finally, finally approved on October 9, 2013 and this transfer is the last thing to be done to conclude these years of stress and I'd say torture even, imposed by a clueless, feckless board on its successors and our town. Fortunately for us, the final settlement amount was whittled down to  a mere $11,396,505.

For perspective, the entire operating budget of the District has been around $4.9 million yearly, but with the income from the Solid Waste Franchise gone, it will now be less. The periodic rate adjustments to our bills will no longer be determined by our LOCSD board, but by the County. The $151,000 in yearly franchise income, flushed down the toilet as it were. And that is the event on our agenda for the day after World Toilet Day. Get the facts here.

Friday, November 08, 2013

Infeasible Is Not A Dirty Word

Much ado has been made in the blogoshpere and public meetings of late over "dewatering." For those who have not chosen to fully live every phase of the sewer project, or prefer to leave water matters in the hands of the professionals, this water is that which is being pumped out of the trenches where the contractors are putting in the sewer pipe in the low lying areas. It is important to know that 1) You cannot lay and seal the pipe in water; 2) Anywhere from 300,000 gallons to 1 million gallons of water is going into the bay DAILY as a matter of natural course.

The County and contractors have been under fire by certain long-standing sewer critics for not using all of that water for recharge (at Tri-W, or rather the Mid-Town site, gets as much as it can percolate), or for dust control on the roads. And at Broderson. Some of that water has been pumped into the bay as there has been no other feasible place to put it, meaning trucking it "somewhere" or running pipe and pumps to some of the town's drainage basins would have had huge logistical and cost impacts.

The most definitive answer regarding Broderson, the place the sewer critics are pushing to put it lately, came from the County yesterday in the form of a letter from Dave Flynn, Deputy Director of Public Works to Kenneth A. Harris, Executive Director of the Central Coast Regional Water Control Board. Broderson is not feasible. Read the attached letter to see why.

The point is, the low lying areas needed to be dug up when there is no rain. Broderson has been a very lengthy process with all of the environmental work that was necessary and the project could not wait around for it to be finished.

To habitually scream 8 to 16 million gallons of water going into the bay!, with NO ACTUAL figures is just plain wrong, not to mention the irresponsibility of churning up panic or anger in the general populace by false statements. We now know that since July, there has been on average 750,000 gallons of dewatering a day. The average land disposal per day has been 550,000 gallons per day; of that, 400,000 gallons per day to Tri-W and 150,000 gallons per day used for construction purposes. So an average of 200,000 gallons of water is going into the bay (keep in mind 300,000 gallons goes in there NATURALLY).

So what is all this about? Critics latching onto a plausible-sounding argument with which to bash the County. Frankly, that just sucks and I am pretty sick of it.

I can only hope that County will consider the source of this dissension; it is tiny, long-standing in hating-every-aspect-of-this-or-any-other-doable-sewer-project, and while annoying, very annoying, it is only a small part of the populace who is otherwise getting along good-naturedly with the bumps and beauties of the project.






Another Sort Of Sewer Tour

Yesterday I posted a different sort of sewer tour. One that was lighthearded. This video is hard core, depressing. You might not want to watch it. Sewers have different uses. I guess these people are glad they have someplace to hide.

Anyone whining about what is happening here really needs a reality check about what happens in the other parts of the world.



Thank you Thomas Morton for making this video.

Thursday, November 07, 2013

Plan Ahead For Your Summer Vacation in Paris!

I ran across this video on YouTube and thought we sewerphiles might like to view the sewer tour under the streets in Paris. This place has a sewer museum! I'm not sure that we could apply that idea here, but we do have a rather famous sewer history in Los Osos. We could sell manhole cover keychains, grinder pump coffee grinders (scaled down of course), sewer rats (ours would have to be pretty small, our pipes are dinky), and Eau de Toilette, a scent yet to be determined!



Thanks to Chris of Yellow Productions!

Sunday, November 03, 2013

"Fatberg" in London Sewer

We septic tank users don't often, if ever, get a view into the tank. Because pumping is expensive, and we are sitting on top of our water source, most of us try to be mindful of what we put in there. But in 2016 we will all be hooked up to our new sewer, and since some of us are imports from cities where we really don't give much thought to what goes down the potty, here is a glimpse of what could happen, on a much smaller scale of course, to our spanking new pipes (try not to gasp or puke, or maybe just don't go to this link):

http://www.dailymail.co.uk/news/article-2417381/The-Fatberg--bigger-Londons-dirty-secret-grown-THREE-tonnes-just-month.html

So think before flushing. Our town's collective septic system at Bayridge Estates had a blockage on October 24 due to large chunks of grease and wipes. So now is a good time to start practicing good sewer stewardship as ghastly as that sounds.

Sunday, October 27, 2013

Saturday, October 26, 2013

Sewer Work on Sixteenth

Similar to, but different from the reconstruction of the tanks on16th (and the street being torn up for the new piping that went with it), the sewer construction is the most exciting thing to hit 16th. OK, the broken unmarked water pipe near the bike path was high drama a few days back, but it was over pretty fast. This is going on for a while.


It started with the pot holing.


Then the street was unzipped.


Water applied at every step to keep down the dust.


Electrical wires lifted out of the way.


Coming up the hill.


Digging sand.


The point of digging, placing pipes. Rather a pretty color!


The trench boxes are moved around with surgical precision.


Tap, tap, tap. Then more digging inside the box.


Plates go down to keep the sand contained.


When the pipe is in the trench boxes come out. 
Note the lift in the back, they are pretty heavy.


Plates arrive to cover the excavation.



Look to the upper left at the holiday appropriate antenna decor!

There is so much more to say about the mind boggling dexterity of the equipment operators. How they lift, trek, nudge and tap these giant hunks of steel as though they didn't weigh tons.
And the fantastic project coordination with the many steps that require perfect timing between the different parts of the team—the guys constantly measuring, guys cutting pipe, so as soon as the trench is ready, in goes the pipe, the street sweeping and watering both with the equipment and by hand, new water arriving via truck, two trucks lined up to keep the dirt coming up and away from the trench, the dirt coming back to go into the newly piped section, putting on the plates with some hot asphalt to keep them firmly in place. Today is Saturday and the watering trucks came twice (while I was paying attention). 
I got nothing done Friday watching this oh, so, beautiful show.








Tuesday, October 22, 2013

16th Street Water Works!


Well, it was a tough day on 16th Street for both the ARB construction guys and our own CSD water crew (and for residents and one of the schools too). There was an unmarked water pipe (where have we heard that story before?) a tad north of the El Moro Bike Path and one of the big machines hit it. I missed the first part, the fountain, but will show some later shots of the event. I only knew something had happened because I went to wash my hands, two drops of water came out, then nothing.

The CSD crew had already jumped into action, Frank was running up the street to the tanks to turn something off and our other CSD water crew guys were locating the shut off valves to shut the water off, of which there were more than one.

The ARB crew had to halt work until the water stopped off course, but some brave residents motored out of the mess with no problem.

Fortunately the drainage project at the bottom of 16th had been set up years ago and it worked to get the water across and under Paso Robles down to Walker Ditch and beyond.

Once the water stopped, the ARB crew was all ready to go with a new section of pipe and two couplings. So as one guy said, "we have an upgrade!"

The main things about this, no one was hurt, no homes flooded and the repair was done amazingly fast. Sure, too bad about the water loss, but now that the CSD is FINALLY out of bankruptcy, maybe some money will be available to do some capital improvement upgrades which have been on the back burner for years.

I had two in-depth conversations, one with with ARB's Paul Gallagher, Project Manager and one with HDR's Jim Brantley, Construction Manager. They both were on top of the problem immediately. They both have had experience with big projects like this, so this was not anything new to deal with, they had seen it all before. We are in good hands, no question, these guys and their crews are quite amazing and we are lucky to have them working for us!

Looking South

Drainage at Work

The Hidden Pipe

Looking North

All Fixed

Thursday, October 17, 2013

Government Shutdown Impacts the LOWWP

The New Times' latest issue which came out today has a story on the impacts of the government shutdown to our county. Our sewer project funding took a hit, which hopefully, since the shutdown is over, will go back to normal money-wise. Sad, sad, sad that this happened, not simply for our project as the broader picture is far worse.

Read the New Times story here and look for the heading, Effects on local government:

http://www.newtimesslo.com/cover/10142/fed-up-octobers-partial-federal-government-shutdown-is-just-the-latest-manifestation-of-the-cyclical-crises-plaguing-slo-county-and-the-nation/

Monday, October 14, 2013

Sewer Related, That's For Sure

Today the CSD put out a press release with the FINAL results of the bankruptcy caused so many years ago by stopping the last sewer project. I'll put a copy up here in case you would like to read what it says.

Sad, sad, sad, so much wasted time, money and water (as we could not conserve nearly so much water without a sewer project to fund it.) Oh well.


Friday, October 11, 2013

Regional Board's Response to LOCSD Letter

I heard about this letter Wednesday and here it is—the response from the Regional Board to the LOCSD's letter on de-watering. Looks like they are fine with what the contractors are doing and if they are not concerned, so neither should we be. To the hair-on-fire commenters on other online places, the fire is officially out.



Update From Coastal Commission - Amendment Approved

Yesterday's meeting had a Los Osos item on the Consent Agenda for the Central Coast. It was called an "immaterial amendment" and it was to move the stand-by power station for the Lupine Pump Station. There were 9 items on this agenda, and of course, the only one to engender an objection was the Los Osos item. However it did not change Staff's opinion to allow the amendment to pass and the Coastal Commission agreed. This took a grand total of 40 seconds. Access the documents for this item at this link:

http://losewersaga.blogspot.com/2013/10/california-coastal-commission-hears.html

One wonders, had the objections not been there, and as the staff report made full approval of this amendment, was there any need for the expense of sending Mark Hutchinson and Paavo Ogren to San Diego for 40 seconds? My advice to the obstructionists? Don't. Please don't. You are costing this project unnecessarily—once again.

If you are into CCC geekiness, you can access the video of the meeting off this page, but for 40 seconds 25 minutes into the meeting, better to read the outcome here.

Thursday, October 10, 2013

Doorhanger!

Yippee!!! Got my 72-hour door hanger!!! Can't wait for the construction to begin!!! (The 16th Street tank project with the new water lines was the opening act a couple of years ago and that was fascinating!)

Wednesday, October 09, 2013

Dig Los Osos Advises Caution

The pipe that will take the treated water back to town will begin installation today, 10-9-13. It will travel from Clark Valley Road back to the disposal sites. Expect traffic delays and be careful! This return pipe will take less time to install than the outbound gravity lines and force mains and you can read the full story here:

http://www.diglososos.com/2013/10/08/traffic-alert-work-on-los-osos-valley-road-resumes/

Tuesday, October 08, 2013

California Coastal Commission Hears Project Amendment

Thursday October 10, 2013 the CCC will hear a proposed amendment to the Coastal Development permit for the sewer project. The Executive Director deems the amendment as immaterial and recommends that the change as it is consistent with the original CDP approval. However, if objections are received, the amendment won't be passed unless three Commissioners agree to the immateriality of the of the Executive Director's determination. If they do not, the application shall be processed as a Material CDP amendment.

Please read the report below.














Friday, October 04, 2013

Part of the Sewer Plan, the HCP

One of the conditions to the sewer project is the Habitat Conservation Plan (see the need for this and what it is at this link to project conditions - No. 92, page 37 of 98 if you open the document in Acrobat).

We haven't heard much about it, but it will be unveiled next week at the South Bay Community Center, Tuesday October 8. There will be two sessions for you to learn and to give input. The LOCAC website lists the times at 3:30-5:30 p.m. and at 7:30-9:00 p.m..

I have a copy of the old 2005 plan, but all the links to a copy of that plan online seem to be dead. So to get an idea of what this is about, here are some useful links:

For mostly what you need to know about what the plan is, click the blue links or just scroll through to the bottom:

https://www.federalregister.gov/articles/2013/09/19/2013-22778/habitat-conservation-plan-for-the-community-of-los-osos-san-luis-obispo-county-ca-notice-of-intenthttps://www.federalregister.gov/articles/2013/09/19/2013-22778/habitat-conservation-plan-for-the-community-of-los-osos-san-luis-obispo-county-ca-notice-of-intent

Lots of info here on the County document at this link:

http://www.slocounty.ca.gov/Assets/PL/environmental/Los+Osos+Communitywide+Habitat+Conservation+Plan/NOP.pdf

And here is the timeline/status report:

http://www.slocounty.ca.gov/Assets/PL/environmental/Los+Osos+Communitywide+Habitat+Conservation+Plan/statusreport.pdf

$300,000 in grant funds were awarded to SLO County from the Coastal Impact Assistant Program to pay for the state and federal EIR reports needed for this plan required for the wastewater treatment facility by the California Coastal Commission.

Public participation is invited and encouraged, so I hope to see you there!

(Not to confuse you, but this is not the same thing as the Habitat Management Plan which fulfills Special Condition 3 of the CDP or Coastal Development Permit.)

Wednesday, October 02, 2013

New Tweet from Dig on LOVR Traffic

Dig Los Osos has posted a new article about the traffic impacts on LOVR due to construction. I failed to think about that today and sat through a 10-minute delay! Plan ahead!

Read the story at this link:

http://www.diglososos.com/2013/10/02/traffic-update-work-on-los-osos-valley-road-continues-expect-delays/

Tuesday, October 01, 2013

Reclamation Facility On Supes Agenda 10-8-13


Board Business:


19. Letter transmitting plans and specifications (Clerk’s File) for the Los Osos Wastewater Project, Water Recycling Facility, Los Osos for Board approval and advertisement for construction bids and submittal of a resolution making findings pursuant to Public Contract Code Section 3400 designating product requirements. The recommended bid opening date is Thursday November 21, 2013. District 2

When the support documents are uploaded, I will include a link.

Here is the link to the support documents:

http://agenda.slocounty.ca.gov/agenda/sanluisobispo/Proposal.html;jsessionid=41E21522081D225E794B77C2A97F8423?select=2653

Monday, September 30, 2013

CCC Proposes Permit Amendment

Dated September 26, 2013, the proposed amendment to the Coastal Development Permit (CDP) would allow for the standby power building associated with the Lupine Pump Station to be relocated to a parcel with a greater distance from wetlands, where no tree trimming or removal would occur and that has no suitable habitat for the endangered Morro shoulderband snail. The amendment would also amend Special Condition 4 to allow the recordation of the required easement to occur prior to the operation of the treatment plant rather than prior to the construction of the plant.

This letter arrived in the mail on Friday, September 27. The Commissions reference number for the proposed amendment is A-3-SLO-09-055/069-A2.



The Executive Director has determined this change to be immaterial as it is consistent with the Commission's original CDP approval, the certified LCP, the Coastal Act's access and recreation policies.


Tuesday, September 17, 2013

BOS, 9-24-13 LOVR Road Widening Ahead


  1. Submittal of bid opening report for Los Osos Valley Road Widening between Doris Avenue and Pine Avenue in Los Osos, and to award the subject contract to R. Burke Corporation, the lowest responsible bidder, in the amount of $203,698. District 2. 

Friday, September 13, 2013

Sunday, September 08, 2013

Lacy's Observation


I wish I'd taken better notes last Thursday night at the Los Osos Community Services District meeting where "THE LETTER" was the most anticipated agenda item. An agenda item with no staff report as a friend noted. Odd, but the reason became clear once that Item 12 came up.

Lacy said something to the effect of getting away from partisanship around the dewatering issue and just explaining to the TV audience the basic facts around water, like how much is an acre foot, so people in TV-land would understand what we all were talking about (wisely presuming that they are not all sewer geeks like the in-house audience). Sort of educating the public as it were.

To recap from my article below on this topic, "THE LETTER" was to be (or not to be) the desired result of the discussion on whether to write to the Regional Water Quality Control Board demanding that they tell the County to tell the contractors to stop sending that trench de-watering water into the bay. You can see how this would be a "hair on fire" topic for those who stopped the last project, (stopping the even greater conservation efforts than the current project that it afforded the water supply starting back in 2008. Imagine, huge water savings since 2008! That's FIVE YEARS!) That's right, I was being facetious. But hey, what's not to hate about yet another sewer project if you can do it with a water fight!

OK, full disclosure, I spoke right before Lacy did and I was the ONLY speaker to unfailingly support the last project AND this project. The other speakers that night ranged in opinion from denying that we needed a sewer to throwing verbal rocks at the Supes at their almost weekly meetings for not stopping this "atrocity of a sewer" that is being built now. So I don't really know if she was referring to all of us who were giving our partisan opinions at the lectern or just mine, which was shouted at from the back of the room.

If you are new to this topic, the contractors are de-watering the trenches in the low-lying areas. The water is being used on the roads for dust control, re-absorption into the ground at Tri-W—the Mid-Town site—and that water which has no place else to go is going into the bay.

The impetus for writing then is, as a water purveyor, to save that water and stick it back into the ground somewhere.

Some salient points for this discussion however:

• No one at the meeting knew how much water was going into the bay; 
• Not one of the other two water purveyors was to be part of this letter, which brought up the obvious, "why not?" You'd think having just completed together a 300+ page Basin Report, on the future of ALL water use for Los Osos after six or seven years of work it would be odd that they would not act together IF the water supply was in jeopardy? (Weren't they asked? Didn't they notice or care?) Wouldn't the case to the Water Board be that much stronger if all three purveyors spoke with one voice? But then, if the water going into the bay wasn't quantified.............

In past weeks, some of the night's speakers had bandied about numbers like "eight to sixteen million gallons going into the bay DAILY!" at the Board of Supervisor's meetings, (those numbers given as a possibility in the Dewatering Plan for the trenches). At this meeting however, the number had been softened to "unknown" amounts.

I already see some holes in trying to make a persuasive case to the Water Board.....

Here is a much bigger hole. The Environmental Impact Report for the project (approved by the Water Board) states, 

"The findings of this study conclude the following:
  • The impacts of shallow groundwater disposal during project construction would be less than significant if beneficially reused during construction (i.e., dust control and soil moisture conditioning of backfill soils) and/or disposed to storm drains or storm water percolation basins in accordance with RWQCB permit conditions....."
(Storm drains in case you were unaware, go into the bay.)

In that EIR you can also find this chart of water lost to the bay:


Now, in the spirit of educating the public, an acre foot of water is 325,851 gallons. Sweet Spring (at Sweet Springs) flows at the rate of 292 acre feet a year, making the yearly gallon amount lost to be 95,148,492. That is from ONE spring. Ninety-five MILLION. And there are other seeps and marshes along the bay. Of course this is going to vary from year to year depending on rainfall and septic returns and yard watering and all that, but at least we have an idea in a report written by experts.

So down to the pumping amount observed at the trenching by the bay as mentioned in the meeting: One six-inch pipe with an estimated 20 gallon a minute pump. That is 28,800 gallons in one day if it runs 24-hours. But does it? How many days has this gone on? We don't know. But isn't it water that would be draining into the bay anyway?
The Water Board knows these amounts. Here are some tidbits from the final EIR (or FEIR).
Appendix Q FEIR 

Page Q.5.2-1
Construction activities may require dewatering, however, the dewatering activities are not expected to substantially alter the quantity of existing groundwater supplies. Therefore, the proposed construction activities associated with the Preferred Project would result in a less than significant impact on groundwater supplies.
 
Page Q.5.2-3
Based on a review of the additions and modifications of the collection system facilities, the Preferred Project may require additional dewatering of the existing groundwater supplies during short-term construction activities within the perched aquifer. Based on a review of the additions and modifications of the collection system facilities under the Preferred Project, no substantial dewatering of the existing groundwater supplies within the perched aquifer would occur.

Please see page 4 of this document for what the Water Board knows about the project. Really, read the de-watering part! It is right from the pen of the Central Coast Regional Water Quality Control Board!

The LOCSD's letter was hastily drafted at the meeting and we don't yet know the final wording, but it basically says, "Water Board, tell the County to stop the contractors from de-watering to the bay and hurry up completing Broderson so we can put the water there instead." (Broderson is where most to the treated water will go once the wastewater project is on-line. It is close to completion.)

Did the LOCSD read the FEIR or the Water Board's staff report mentioned above? Will they look uneducated to make these demands? Would they ask, "where are the other water purveyors?" Could there possibly be any unintended consequences from this letter (where have we seen that before around a sewer project....), you know, like project delays, change orders, a longer time to complete the project? Or will the letter go unheeded, thereby giving the sewer-haters a new (old) target for vitriol, the Water Board!? 

Is caving to the unfounded demands of those who brought us the last hideous batch of unintended consequences the best path for the LOCSD? 

Well, good or bad, writing the letter certainly got those strident voices to calm down and blow the board kisses by the end of the meeting (those very same voices that had bashed the board at the prior meeting no less)!

So back to Lacy and her admonition about partisan politics. She may not know just how prescient she was with her wish. Who IS playing the politics here?

Saturday, August 31, 2013

Dewatering Letter, To Bay Or Not To Bay?

Thursday, September 5, 2013, the Los Osos Board of Directors will have a discussion on the sewer contractors putting water drawn from trench dewatering into the bay. This had been a hot topic by the usual Los Osos speakers at the Board of Supes. To be decided: shall a letter be written to the Regional Water Quality Control Board asking them to tell the sewer contractors to stop putting water in the bay?

Two contractors ARB (access their early dewatering plan here*) and W.A. Rasic (access their early dewatering plan here**)  have needed to pump water out of the ground while digging trenches so that pipe can be safely installed. The water you see the contractors spraying on the roads for dust control is from the trenches. Water has been unloaded onto the Mid-Town Property (formerly known as Tri-W) by ARB and according to their plans, more water is to go to the Fairchild retention basin. Some water has been going down culverts as well, but quantity and source are unclear.

The comprehensive Dewatering Plan written by CDM Smith was released in March of 2012, but not until recently were the crews in the areas where dewatering needs to occur.

That plan states on page 1 (color emphasis mine),
"This report has a preliminary recommendation to use a four-stage approach. The first stage is to use water for construction use (dust control, etc.) since no groundwater retention sites will be available when work starts. Stage two would continue to utilize construction use and would add the new Mid-Town retention site and the existing retention basin sites for groundwater disposal while the Broderson leachfield system and the recycled water pipeline from the treatment plant to the Broderson effluent disposal site are being constructed. During stage three, when the Broderson leachfield site and the recycled water pipeline have been constructed, both the Mid-Town retention site and the Broderson leachfield site will be operational and construction of the gravity collection system and pump stations and force mains can then proceed with the necessary dewatering. The intent would be to pump discharged groundwater to the Mid-Town and public retention basins for land disposal and Broderson for back-up. Discharge to the Mid-Town and existing public retention sites augmented with the Broderson leachfield site appears to be a viable and cost-effective means to dispose of the anticipated flows. Flow estimates range from approximately 620 to 1,300 gpm for one dewatering area, and 2,500 to 4,900 gpm for four concurrent areas throughout construction. Groundwater production in excess of 6,500 gpm would require a fourth stage involving agricultural reuse along Clark Valley Road. This would be necessary only if the groundwater production exceeds what could be disposed of with the combined capacity of the construction use plus Mid-Town and existing retention sites plus Broderson leachfield site. Treatment and disposal to the storm drains are a possible optional disposal method."

This plan went before the Regional Water Quality Control Board September 6 & 7, 2012.

For background, the perched aquifer and upper aquifer are overfilled due to septic discharges and are presently dumping an estimated one million gallons into the bay daily and have been doing so for years (more conservative estimates are for 300,000 gallons per day). I asked John Waddell if this would stop when the sewer has been running for a while. He said no, there would still be some discharge. So some amount would seem to be a permanent condition.

The Regional Board has sent a letter to the County concerning this water August 7, 2013. There were many questions on the W.A. Rasic plan and just two on the ARB plan. I can't find this letter online or I would provide a link. No where in the letter does the Water Board accuse the contractors of malfeasance or illegal discharge.

Rasic needs to fill out their dewatering intentions in order of importance and more fully. Both ARB and Rasic need to explain their contingency plans for rainy season.

Questions for the LOCSD board should revolve around the information they divulge with their own meeting with County staff***. Has water actually been discharged to the bay and how much? How much water is actually being pumped out of the trenches? Have ARB and Rasic updated their plans to accommodate the questions by the Water Board? If not, when will this be done? If discharge to the bay is the only feasible option, when will the Water Board approve it? (October 9, 2013 is their next meeting as the September meeting was cancelled.) When is Broderson going to be ready to receive water? Once questions are answered, the need for a letter will emerge (or not). And a refutation of some of the really infeasible ideas, such as trucking water off site to unnamed destinations should be put to rest.

Given the information above on the disposal options, the bay may be our last hope if there is just too much water. But given the amount already leaking into it DAILY, panic as to lost water supply might be just another angry disapproval for this wastewater treatment plant by certain long-time critics than a dangerous condition for our water companies.


* June 14, 2013 is a more current plan, unfound online.

**July 23, 2013 is the date of the current plan but I couldn't find it online.

*** Only two Directors met with staff, so it was not a violation of the Brown Act.

Saturday, August 24, 2013

Inextricably∞Tied


We have one source for water at present in Los Osos. Since water quality and quantity are so tightly tied to the present sewer project, and needing more of it is the reason for our future water infrastructure projects, it seemed worth a mention on this sewer blog. 

You have a new opportunity to get a water education and make suggestions on the future of our water at the Los Osos CSD's presentation of the Basin Plan by District Engineer Rob Miller on Thursday, August 29, 6:00 p.m. at the South Bay Community Center. See the announcement at this link:


As some of you may be aware, the Draft Basin Plan, which is the impetus for this meeting, has been released for public review. I doubt droves of us are going to read the 300+ page full version, but a reading of the Executive Summary is not too tough and since the costs to fix things are included, it is really worth the read. Wastewater treatment is the first part of the big picture, creating a sustainable water supply so we can continue to live here is the second.

If you want to read the entire plan, you may download the entire 10mb file at this link:


ALSO, another reason to put this information out here is to get as many of you as possible to show up at that meeting. For anyone with a vacant lot that they would like to someday build on, this meeting will be of interest. Realtors too might want to get educated. We should all care as none of us will be living here without water. 

No plans exist at this time to film the meeting (I hope that changes!), so show up to get the info yourself firsthand.

UPDATE: The meeting WILL be taped, so presumably a disc will be at the front desk some days later for home viewing.

July 2013 Project Update

You can find that report at this link:

http://www.slocounty.ca.gov/Assets/PW/LOWWP/PM+Monthly+Update+July2013.pdf

Sunday, August 04, 2013

Friday, August 02, 2013

ISJ Work Online Friday August 2, 2013

At the August 1 meeting of the Los Osos Community Services District, it was great news to hear that the very, very, very, very tardy ISJ work would become public on the LOCSD website August 2, sometime during the day. The Executive Summary and the Draft Basin Plan will be posted there, copies will go to the library and CDs will be available for check-out at the LOCSD office (remember, there are new office hours). The link to the site is here:

http://www.losososcsd.org/cm/Home.html

There will be sixty days of public review and a TBA presentation of the plan. All comments on the plan must be in writing, but it isn't clear to me just where these comments are to go.

How is this "sewer project information?" WATER! No dirty water, no sewer, but that is hardly the case here in LO. OK, it is a condition of the Coastal Commission permit for the project that there be a "Basin Plan."

This 2011 staff report gives a good overview, here is a cut'n'paste:


Los Osos Wastewater Project 
March 2011 Status Update

EXHIBIT “B”

UPDATES ON THE BASIN MANAGEMENT PLAN, THE HABITAT CONSERVATION PLAN AND THE LOCAL COASTAL PLAN

Los Osos Groundwater Basin Management Plan

Efforts to reach a settlement under existing groundwater litigation are proceeding under the Interlocutory Stipulated Judgement (ISJ) process to develop a basin management plan to balance the basin for existing and build-out demand. The ISJ group, which consists of the County and the three community water purveyors (Golden State Water Company, Los Osos CSD, and S&T Mutual Water Company), released a basin update in May 2010, which includes the following:

  • Estimates of the safe yield of the basin water supply were updated in 2009. The current demand, from all users, is theoretically within the safe yield according to Basin modeling. However, under the model the water purveyors need to redistribute their well pumping between the upper and lower aquifers and from west to east in order to balance the basin, and the model results need to be confirmed for actual Basin conditions.
  • Recent monitoring has found that the rate of seawater intrusion has accelerated following three years of drought, particularly through advance “fingers”. 
  • A peer review has found that the technical groundwater analysis and modeling provides usable results and can reasonably be used to implement a Basin Management Plan, provided there is ongoing monitoring and analysis. 
  • The Los Osos Wastewater Project will include several actions that benefit the water supply in the community and be complementary to other basin management actions currently being considered.
  • The water purveyors, through the ISJ efforts, are investigating many potential actions to incorporate into the Basin Management Plan in order to balance the basin and stop seawater intrusion.


The ISJ group intends to release a draft Basin Management Plan within the next few weeks. As stated in the May update, the overall basin yield is within the current demand and planned wastewater actions will provide additional benefit to the water supply through conservation and reuse. The result will be some additional supply for new development and, while not yet certain, it is hopeful that through the planning process and careful allocation of water resources there will be sufficient supply to meet build-out demand for the community.

Also useful to understanding how all the water measures fit into the big water puzzle is this document, The Water Conservation Implementation Plan for the Los Osos Wastewater Project.

Having done a bit of snooping, I found this link which suggested that there will be a "water market" and a "watermaster."